Project Tasks
Project Tasks are the individual elements of a project that need to be competed, these could be anything from meeting and project management time to the Tasks that physically need completing within the Project.
Modules > Projects > Project - Tasks Groups - Project Task
The link will open the Tasks Groups / Project Task grid. It is a grid view that can be customised and sorted as normal.
To add a new Project Task click New , to edit an existing Project Task click Edit . A pop up window will appear which will allow the creation or amendment of a Project Task.
Name |
From the drop down select an Instruction set for the Project Task - this can be manually entered if required. |
Priority |
From the drop down select the Priority - for more information see Priority |
Type |
From the drop down select the Project Task Type:
- Project Task - a standard Task within a project
- Move Task - a Task to move Contacts or Assets from one location to another. See Project Move Tasks.
|
Description |
Enter a description for the Project Task. |
Contract |
From the drop down select the Contract - for more information see Contracts |
Compliance |
From the drop down select the Compliance Type- for more information see Compliance Types |
Category |
From the drop down select the Category - for more information see Task Category |
Discipline |
From the drop down select the Discipline - for more information see Discipline |
Building |
From the drop down select the Building - for more information see Building Register |
Location |
From the drop down select the Location - this will be filtered by the Building selected - for more information see Location Register. |
Cost Centre |
From the drop down select the Cost Centre - for more information see Cost Centres |
Cost Code |
From the drop down select the Cost Code - this will be filtered by the Cost Centre selected - for more information see Cost Codes. |
Task Group |
From the drop down select the Task Group - this will auto populate if the Task has been raised from the Task Group - for more information see Project Task Groups. |
Owner |
From the drop down select the Task owner - this list is connected to User Accounts |
Asset |
From the drop down select the Asset - for more information see Assets |
Req. ID |
Enter a Req ID. |
Source |
From the drop down select the Caller Source - for more information see Caller Source |
Estimates
|
|
Start Date |
Enter the estimated start date for the Task. |
Finish Date |
Enter the estimated finish date for the Task. |
Est. Time |
Enter the estimated time to compete the Task in hours. |
Estimated Duration |
Enter the estimated duration of the Task in hours. |
Total Est. Time |
Auto calculated by multiplying est time and number of staff. |
% Complete |
Enter a percentage to reflect how complete the Task is. |
No. Staff |
The estimated number of staff required to complete the Task. |
Material Cost |
The estimated material cost of the Task. |
Labour Cost |
The estimated labour cost of the Task. |
Actuals
|
|
Start Date |
Auto populated with the actual start date of the Task. |
Finish Date |
Auto populated with the actual finish date of the Task. |
PO Cost |
Auto calculated with the actual PO cost of the Task. |
Expenses |
Auto calculated with the actual expenses of the Task. |
Stock Cost |
Auto calculated with the actual stock cost of the Task. |
Labour Cost |
Auto calculated with the actual labour cost of the Task. |
Reporter |
From the drop down select the reporter of the Task - connected to Contacts, this can be manually entered if required |
Phone |
Auto populated with the Contacts phone number - this can be manually entered if required. |
Email |
Auto populated with the email address of the Contact - this can be manually entered if required. |
Notes |
Free text notes relating to the Project Task. |
Complete the fields and click Save . Once the Project Task header has been completed and saved a sub navigation will appear to allow additional entities to be assigned.
These include:
- Recharge Codes
- Predecessors
- Events
- Regulations
Recharge Codes
Click to view more detail.
Once financials have been entered on the Project Task, amounts or percentages can be marked as recharged to the Recharge Codes allocated to the Project.
Modules > Projects > Project - Tasks Groups - Project Task - Recharge Codes
The link will open the Project Task / Recharge Codes grid. It is a grid view that can be customised and sorted as normal.
To add a new Recharge Code click New , to edit an existing Recharge Code click Edit . A pop up window will appear which will allow the creation or amendment of a Recharge Code.
Allocation Method |
Check the radio button to indicate whether the recharge amount is to be a percentage or amount in pounds |
Recharge Code |
From the drop down select the Recharge Code. See Projects for more details |
Amount / Percentage |
Enter the amount or percentage to recharge. |
Predecessors
Click to view more detail.
Within a Project certain Tasks should be started before another begins. Predecessors allows a link to be made to Tasks that should be completed before the commencement of the current Task.
Modules > Projects > Project - Tasks Groups - Project Task - Predecessors
The link will open the Project Task / Predecessors grid. It is a grid view that can be customised and sorted as normal.
To assign Predecessors click Assign , entities in the right hand assignment window are connected.
Events
Click to view more detail.
Events can be added to a Project Task, these can be added within the Projects itself or from Task Management.
Modules > Projects > Project - Tasks Groups - Project Task - Events
The link will open the Project Task / Events grid. It is a grid view which can be searched, sorted and customised as normal.
To add a new Event click New , to edit an existing Event click Edit . A pop up window will appear which will allow the creation or amendment of an Event. See Creating / Attaching Event Types for more details.
Regulations
Click to view more detail.
Regulations can be assigned to a Project Task. If an Instruction Set has been used that has Regulations attached these will automatically be assigned, they can be manually assigned if required.
Modules > Projects > Project - Tasks Groups - Project Task - Regulations
The link will open the Project Task / Regulations grid. It is a grid view which can be searched, sorted and customised as normal.