You are here: Task Management > PPM Planner

PPM Planner

The PPM Planner in Concept Evolution provides a graphical means for viewing, planning and rescheduling dormant PPM Tasks to ensure most efficient use of Resources and to aid in viewing for any upcoming scheduling challenges.

When the PPM Planner is initially launched, it will open in a new window with a blank grid.

To create PPMs see Planned Preventative Maintenance - PPMs

Task Management > PPM Planner

The PPM Planner only shows Dormant PPMs, once a PPM has been issued it will disappear from the Planner and be viewable in Tasks.

The PPM Planner can be filtered to make the view of the Planner easier to manage and view. A minimum filter of Contract Group or Contract must be applied.

Available from 4.5.6.0

The PPM Planer Filter bar is on the right hand side of the planner, this panel can be opened and closed by clicking on the dark grey bar

ClosedClick to view - PPM Planner Icons and Descriptions

Complete the required changes and close the window.