Advanced Helpdesk - Schedule Of Rates
If Schedule Of Rates (SOR) are being used for financial calculations and invoicing, the required number of Schedule Of Rate Items must be added to the Task.
Available from 6.0.1.0
The Schedule Of Rates sub navigation will be hidden if the current Task's Contract has no Schedule Of Rate Items defined with a non-Historic status.
Available from 6.3.1.0
The State indicator in the upper corner of the page has been updated to show the new Work Status and the new Approval Status.
The page has been updated to contain three tabs, new fields have been added and some existing fields have been moved to group them more logically in the new tabs:
The toolbar buttons have been updated as follows:
-
The legacy Status toolbar buttons have been removed
-
Functionality has been added to make it possible to manage the Work Status of the Task SOR Item
-
Functionality has been added to make it possible to manage the Approval Status of the Task SOR Item
-
An Upload toolbar button group has been added to make it possible to perform bulk actions for the current Task SOR Item:
-
Uploading Documents
-
Adding Events
-
The save and update system methods for Schedule Of Rates have been updated to be aware of the new Contract Preferences.
Certain automated updates will occur when changing the Work State or changing the Approval State.
Task Management > Advanced Helpdesk - Schedule Of Rates
The link will open the Task / Schedule Of Rates grid. It is a grid view which can be searched, sorted and customised as normal.
Records in the grid have the following icons:
Icon | Feature | Description |
---|---|---|
![]() ![]() |
View / Add Events | Left clicking on the icon will produce a pop up window showing Events, there is also a hyper-link within the pop up window to add Events. |
![]() ![]() |
View / Add Documents | Left clicking on the icon will produce a pop up window showing attached Documents, there is also a hyper-link within the pop up window to add Documents. |
To add a new Schedule Of Rate click New , to edit an existing Schedule Of Rates click Edit
. A pop up window will appear which will allow the creation or amendment of a Task Schedule Of Rates.
Click to view - Schedule Of Rates Details Tab Fields and Descriptions
Click to view - Schedule Of Rates Progress Tab Fields and Descriptions
Click to view - Schedule Of Rates Financials Tab Fields and Descriptions
Complete the fields and click Save and Close . If additional SORs need to be added repeat the process until all costs have been recorded.
Logic Applied Upon Insert Of A Schedule Of Rate Against A Task
Available from 6.3.1.0

Setting the Source
If an explicit value has not been provided for Source (e.g. when a value is set by a call to the web service) the system will set a value in the Source field that reflects whether the Schedule Of Rate was created in Evolution or Connect.
Check for Approval Required
The system will check the value of the Require Approval for new SORs preference for the Contract of the current Task:
-
If not enabled no further actions required
-
If enabled:
-
The system will check the value of the Approval Required for SOR Sources preference for the Contract of the current Task
-
If not enabled no new actions required
-
If enabled:
-
The system will check whether the Cost Total of the Schedule Of Rate exceeds the value of the SOR Approval Threshold preference for the Contract of the current Task:
-
If the Cost Total value does not exceed the SOR Approval Threshold value then no further actions required
-
If the Cost Total value does exceed the SOR Approval Threshold value, the system will set the Approval State to be Approval Required
-
-
-
-
Logic Applied Upon An Update To The Quantity Of An Existing Schedule Of Rate Against A Task
Available from 6.3.1.0

Check for Approval Required
The system will check if the Quantity value has increased:
-
If the Quantity has not increased no further actions required
-
If the Quantity has increased:
-
The system will check the value of the Require Approval for new SORs preference for the Contract of the current Task:
-
If not enabled no further actions required
-
If enabled:
-
The system will check the value of the Approval Required for SOR Sources preference for the Contract of the current Task
-
If not enabled no new actions required
-
If enabled:
-
The system will check whether the Cost Total of the Schedule Of Rate exceeds the value of the SOR Approval Threshold preference for the Contract of the current Task:
-
If the Cost Total value does not exceed the SOR Approval Threshold value then no further actions required
-
If the Cost Total value does exceed the SOR Approval Threshold value, the system will set the Approval State to be Approval Required
-
-
-
-
Schedule Of Rates - Work State Model
Available from 6.3.1.0

State Model - Work States
State Name | Is Default | Description | Display Name |
---|---|---|---|
Active | Yes | Mark as Active | Active |
Completed | No | Complete | Completed |
Not Required | No | Not Required | Not Required |
Approved | No | Approve | Approved |
Returned | No | Return | Returned |
Rejected | No | Reject | Rejected |
Permitted Work State Transitions
Name |
Description |
From State |
To State |
---|---|---|---|
Work Complete |
Mark SOR Item as Complete |
Active |
Complete |
Not Required |
Mark SOR Work Status as Not Required |
Active |
Not Required |
Approve |
Approve Work Completion for SOR Item |
Active |
Approved |
Return |
Return SOR Item to request more supporting information |
Active |
Returned |
Reject |
Reject Work Completion for SOR Item |
Active |
Rejected |
Mark as Active |
Mark SOR Work Status as Active |
Completed |
Active |
Approve |
Approve Work Completion for SOR Item |
Completed |
Approved |
Return |
Return SOR Item to request more supporting information |
Completed |
Returned |
Reject |
Reject Work Completion for SOR Item |
Completed |
Rejected |
Mark as Active |
Mark SOR Work Status as Active |
Not Required |
Active |
Work Complete |
Mark SOR Item as Complete |
Returned |
Complete |
Not Required |
Mark SOR Work Status as Not Required |
Returned |
Not Required |
Reject |
Reject Work Completion for SOR Item |
Returned |
Rejected |
Mark as Active |
Mark SOR Work Status as Active |
Rejected |
Active |
Return |
Return SOR Item to request more supporting information |
Rejected |
Returned |
Work State Change Permissions
A new Permission has been added to control Work state changes in addition to the standard Create, Read, Update and Delete permissions for Task Schedule Of Rates:
-
Approve and Reject Task Schedule Of Rates Work Status - ALLOW
-
Controls access to set the following Work States:
-
Approved
-
Rejected
-
Returned
-
-
Work State Change Comments and Events
The user that instigates a change of the Work State for a Schedule Of Rate will be presented with a pop up, allowing them to optionally add comments to explain why they are changing the Work State. An Event will automatically be created for the Work State change. Any comments entered will be stored against the Event.
Other Work State Change Actions
When moving to the Completed state
All existing logic that sets values for Completed Date fields will be invoked when the Status changes to Complete.
When moving to the Active state
Values in the Completed Date fields will be reset to Null.
Schedule Of Rates - Approval State Model
Available from 6.3.1.0

State Model - Approval States
State Name | Is Default | Description | Display Name |
---|---|---|---|
Not Required | Yes | Not Required | Not Required |
Pre-Approved | No | Pre-Approved | Pre-Approved |
Approval Required | No | Approval Required | Approval Required |
Approved | No | Approve | Approved |
Returned | No | Return | Returned |
Rejected | No | Reject | Rejected |
Permitted Approval State Transitions
Name |
Description |
From State |
To State |
---|---|---|---|
Approval Required |
Request Approval for SOR Item Costs |
Not Required |
Approval Required |
Approval Required |
Pre-approve SOR Item Costs |
Pre-Approved |
Approval Required |
Approve |
Approve SOR Item Costs |
Approval Required |
Approved |
Return |
Return SOR Item for more Cost supporting information |
Approval Required |
Returned |
Reject |
Reject SOR Item Costs |
Approval Required |
Rejected |
Approval Required |
|
Return SOR Item for more Cost supporting information |
Returned |
Approve |
Approve SOR Item Costs |
Returned |
Approved |
Reject |
Reject SOR Item Costs |
Returned |
Rejected |
Approval State Change Permissions
A new Permission has been added to control Approval state changes in addition to the standard Create, Read, Update and Delete permissions for Task Schedule Of Rates:
-
Approve and Reject Task Schedule Of Rates Approval Status - ALLOW
-
Controls access to set all Approval States
-

Approval State Change Comments and Events
The user that instigates a change of the Approval State for a Schedule Of Rate will be presented with a pop up, allowing them to optionally add comments to explain why they are changing the Approval State. An Event will automatically be created for the Approval State change. Any comments entered will be stored against the Event.
Other Approval State Change Actions
When moving to the Completed state
All existing logic that sets values for Completed Date fields will be invoked when the Status changes to Complete.
When moving to the Approved, Returned or Rejected state
The system will check whether the user trying to change the state has the required permission, assuming they have:
-
the Approval Review Date will be set to the current date
-
the Approval Review By will be set to user making the Approval State change