If a Schedule Of Rates is being used to calculate Costs in MRI Evolution it must be attached to the Contract. Individual items can be created against the Contract or a Master Schedule Of Rates can be imported.

Facilities > Contracts - Schedule Of Rates

The link will open the Contract / Schedule Of Rates grid. It is a grid view that can be customised and sorted as normal.

To add a new Schedule Of Rates click New , to edit an existing Schedule Of Rates click Edit . A pop up window will appear which will allow the creation or amendment of a Schedule Of Rate.

To import a Master Schedule Of Rates click Import Master Schedule Of Rates .

Available from 5.8.1.0

Since the addition of States to Master Schedule Of Rates, the import function has been updated as follows:

  • Suspended Master Schedule Of Rates should be imported and values refreshed

    • The state of the Schedule Of Rates linked to the suspended Master Schedule Of Rate will be updated to suspended

  • Historic Master Schedule Of Rates should NOT be imported

  • If any existing Schedule Of Rates are linked to the Historic Master Schedule Of Rates these will be updated to History

  • If any existing Schedule Of Rates are Suspended and linked to a Master Schedule Of Rates that is Active, these will be updated to Active

To create a Master Schedule Of Rates see Master Schedule Of Rates Groups

ClosedClick to view - Schedule Of Rates Items Fields and Descriptions

Complete the fields and click Save. Once the Schedule of Rate Item has been completed and saved it will be available to be added to a Task in the current Contract.

Schedule of Rate Item Toolbar Icons